• J Eval Clin Pract · Feb 2025

    Optimising Outpatient Registration System Implementation Using Critical Path Method: A Case Study.

    • Dan Hong.
    • Department of Information Center, Shijitan Hospital of China Capital Medical University, Beijing, China.
    • J Eval Clin Pract. 2025 Feb 1; 31 (1): e14254e14254.

    BackgroundToday, hospital information systems (HISs) play an irreplaceable role in hospital management. At present, HIS construction projects in many hospitals have faced the setback of 'project quagmire' to varying degrees. The critical path method (CPM) mainly aims to find the critical path, thus managing project progress.ObjectivesTo explore the importance and practical application of the CPM to the management of HIS project schedules.MethodsThis study used the construction project of a hospital's outpatient registration subsystem as an example. CPM was used to determine the critical path. The time and workload required for the project were calculated using the forward and backward extrapolation methods. The earliest start time and earliest completion time as well as the latest start time and latest completion time of each task could be calculated using the forward and backward extrapolation methods. The path with the longest construction period was determined to be the critical path, and the unit speed rate of each activity was calculated on this basis. Then, the time schedule of the outpatient registration subsystem was compressed and the project schedule optimised.ResultsPath 3 [outpatient registration demand analysis (A)-basic data preparation (C)-subsystem test (F)-simulation test (G)] was determined to be the critical path according to the construction period, and the task time was compressed on this basis. Considering many factors, the time of the subsystem test task (F) was reduced from 7 weeks to 4 weeks. The total cost was saved by 1000 yuan, which not only ensured the progress ahead but also saved the overall cost.ConclusionThe CPM could effectively measure the completion and deviation of each stage of the registration system project, which provided an effective guarantee for the subsequent schedule compression to ensure that the project was completed as scheduled and was of sufficient quality. However, all conditions had to be considered comprehensively; doing otherwise would lead to increased risks and costs.© 2024 John Wiley & Sons Ltd.

      Pubmed     Copy Citation     Plaintext  

      Add institutional full text...

    Notes

     
    Knowledge, pearl, summary or comment to share?
    300 characters remaining
    help        
    You can also include formatting, links, images and footnotes in your notes
    • Simple formatting can be added to notes, such as *italics*, _underline_ or **bold**.
    • Superscript can be denoted by <sup>text</sup> and subscript <sub>text</sub>.
    • Numbered or bulleted lists can be created using either numbered lines 1. 2. 3., hyphens - or asterisks *.
    • Links can be included with: [my link to pubmed](http://pubmed.com)
    • Images can be included with: ![alt text](https://bestmedicaljournal.com/study_graph.jpg "Image Title Text")
    • For footnotes use [^1](This is a footnote.) inline.
    • Or use an inline reference [^1] to refer to a longer footnote elseweher in the document [^1]: This is a long footnote..

    hide…

Want more great medical articles?

Keep up to date with a free trial of metajournal, personalized for your practice.
1,694,794 articles already indexed!

We guarantee your privacy. Your email address will not be shared.